Proactive bi-level geptep with storage considerations

tipo de documento semantico ckh_publication

Ficheros

IIT-18-046A.pdf
Tamaño 1407344
Formato Adobe PDF
Autor
González Romero, Isaac Camilo
Wogrin, Sonja
Gómez San Román, Tomás
Estado info:eu-repo/semantics/draft

Resumen

Idioma es-ES
Idioma en-GB
Resumen

Under the current European market environment, transmission companies (TRANSCOs) have to decide network expansion by maximizing social welfare while the generation companies (GENCOs) decide their expansion with the aim of maximizing their own profit. This process, in addition to increasing penetration of renewable energy, storage and distributed generation, might create contradictory incentives, which represent a rupture between short and long-term signals. Therefore, this paper proposes a bi-level formulation for the generation and transmission coordination problem (GEPTEP). We consider a proactive framework in which a centralized TRANSCO represents the upper level while the decentralized GENCOs, that trade in the market, represent the lower level. As a novel feature, a representative period framework is employed, which allows us to consider operation of in both short and long-term storage technologies. A case study is presented to compare the results between a one-level cost minimization framework and a bi-level proactive framework.

Tipo de archivo application/pdf
Idioma en-GB
Tipo de acceso info:eu-repo/semantics/restrictedAccess
Fecha de modificacion 04/03/2024
Fecha de disponibilidad 05/05/2022
fecha de alta 05/05/2022

Shared with: