CompartidoEl 24/11/22 por Comillas
Working Paper

Closed-loop two-stage stochastic optimization of offshore wind farm collection system

tipo de documento semantico ckh_publication

Ficheros

IIT-20-054A.pdf
Tamaño 859768
Formato Adobe PDF
Autor
Pérez Rúa, Juan Andrés
Lumbreras Sancho, Sara
Ramos Galán, Andrés
Cutululis, Nicolaos Antonio
Estado info:eu-repo/semantics/draft

Resumen

Idioma es-ES
Idioma en-GB
Resumen

A two-stage stochastic optimization model for the design of the closed-loop cable layout of an
Offshore Wind Farm (OWF) is presented. The model consists on a Mixed Integer Linear Program (MILP)
with scenario numeration incorporation to account for both wind power and cable failure stochasticity.
The objective function supports simultaneous optimization of: (i) Initial investment (network topology and
cable sizing), (ii) Total electrical power losses costs, and (iii) Reliability costs due to energy curtailment
from cables failures. The mathematical optimization program is embedded in an iterative framework
called PCI (Progressive Contingency Incorporation), in order to simplify the full problem while still
including its global optimum. The applicability of the method is demonstrated by application to a realworld
instance. The results show the functionality of the model in quantifying the economic profitability
when applying stochastic optimization compared to a deterministic approach, given certain values of cables
failure parameters.

Tipo de archivo application/pdf
Idioma en-GB
Tipo de acceso info:eu-repo/semantics/openAccess
Fecha de modificacion 06/03/2024
Fecha de disponibilidad 07/06/2021
fecha de alta 07/06/2021

Shared with: